Preparing Your Site for an Expandable Home

Most delivery problems come from the site, not the home. Before your expandable home arrives, the truck needs a clear way in, and the home needs a level, well-drained base to sit on. This guide covers what you need to have ready.

1. Access for the delivery truck

Every expandable home size folds down to the same 2.26m width and 2.52m height for transport. The truck carrying it needs more room than that.

Site access requirements
RequirementMinimumNotes
Access width3.2m minimum3.5–4m is ideal
Height clearance4.0m minimum for trucksMore is needed for crane trucks or near powerlines
Turning space15m recommended for the truckTight turns may mean a crane lift instead
DrivewayMust take the weight of a loaded truckSoft or unsealed ground may need assessment

Walk the path from the street to the final position and look for anything that could block the truck:

  • Low powerlines
  • Overhanging tree branches
  • Fences near the driveway
  • Sharp turns
  • Narrow gates

If a tilt tray can't reach the final position, the home may be lifted into place by crane. Standard crane reach is 6–12m, and larger cranes are available for difficult sites. See delivery and installation for how each method works.

2. A level site

Your site must be level before delivery. An expandable home unfolds on site, and its walls and floor sections need to line up correctly. An uneven base makes that harder and can put stress on the structure over time.

The home can sit on any of these bases, depending on your site and intended use:

  • Concrete footings
  • Steel piers
  • Concrete slab
  • Levelled gravel pad

3. Footings

For footing-based installations, this is our recommended starting layout:

Recommended footing layout
ItemRecommendation
Number of footings6 to 12, depending on model
TypeConcrete blocks or steel piers
Recommended size400mm × 400mm
Minimum depth300mm, depending on soil

Your engineer or certifier has the final say on footing design. Soil type, wind region and whether the home is a permanent dwelling can all change the requirements. The council approval guide explains where the certifier fits in.

4. Drainage

Water should never pool under the home. The ground should slope slightly away from it, with gravel or drainage channels added if needed.

Keeping the underside dry helps prevent:

  • Rust
  • Mould
  • Footings moving
  • Moisture damage

5. Weather on delivery day

Delivery can be rescheduled if conditions are unsafe. Heavy rain, muddy ground, storms, strong winds and any conditions that make a crane lift unsafe can all cause a delay. Queensland's summer storm season is worth keeping in mind when you book.

Pre-delivery checklist

  • 3.2m access width along the whole path
  • 4.0m height clearance
  • Driveway can take the weight of a truck
  • No overhanging branches or powerlines
  • Clear path to the final position
  • Ground levelled
  • Footings or base installed and checked
  • Drainage directs water away from the home
  • Crane payment organised (if a crane is needed)
  • Access gate unlocked on delivery day

Not sure which size your block can take? Compare lengths in the 20ft vs 30ft vs 40ft guide, or check the cost guide for what site works typically add.

This guide is general information, not engineering, legal or building advice. Requirements vary by site, council and intended use. Confirm your specific situation with a licensed building certifier, engineer and your local council.